Target release

DOTB - 20230104

Epic

https://aswb.visualstudio.com/DevOpsToolbox/_workitems/edit/1851

Document Project Status

status
Status
colour
Green
titleDRAFTdeployed

Document owner

Robert Adach

Business POC

Felicia Dennison

Designer

Robert Adach

Developers

Robert Adach

QA

Robert Adach


Note

Project launch date has been moved from 1/17 to 1/24 per Felicia.

Goals

  • The creation and automatic delivery of emails to candidates who have failed the ASWB examination

  • Increase the pass rate of candidates sitting for the ASWB examinations on their 2nd or later attempts.

...

Fifth Theory (TMI) is a sponsorship program that ASWB has contracted with. We will be using this as a remediation tool for candidates who are unsuccessful on the examination.  I 

Assumptions

Requirements

User Story

Importance

Notes

Level of Effort (hours)*

1

As a system I will identify candidates who have failed the examination based on the latest list of scores

Status
colourGreen
titleMUST HAVE

There will be no filtering/exclusions of candidates to be contacted.

4

2

As a system, I will generate an email to be sent to identified candidates

Status
colourGreen
titleMUST HAVE

Per meeting on 12/14, there is no requirement to customize content. LOE reflects this.

4 (9.25 - 11.5 if email content will need to be customized)

3

As a system, I will send generated emails to the identified candidates

Status
colourGreen
titleMUST have

5

4

As a system, I will update a Candidates record with a note reflecting email having been sent

Status
colourYellow
titleSHOULD HAVE
(LOW priority)

1

5

As a system, I will capture email addresses with delivery errors

Status
colourYellow
titleSHOULD HAVE
(LOW priority)

3

6

As a system, I will update the candidates record to reflect delivery errors

Status
colourYellow
titleshould have
(LOW priority)

1

7

As a system, I will record campaign email statistics

Status
colourYellow
titleshould have
(HIGH priority)

  • Email open rate

  • Email click through rate

2 (0 if we can provide read-only access to MailGun reports, or automate reports)

8

First run of the report will be for all failures since January 3rd, going forward it will sent on Tuesday afternoon for

9

*Level of effort indicates the maximum estimated time IT will spend designing, developing, testing and implementing the requirement shown. Not listed is time associated with project management tasks (meetings, official documentation).

...

Date

Action

Notes

11/30/2022

Project Launch

12/14/2022

Requirements completed

1/69/2023

Email content from EA/ED due

Received confirmation from Carl that content is to be delivered on 1/9/2023.

1/12/2023 - received 2nd version of email, additional content update is needed.

1/9/2023

Requirement lockdown

1/13/2023

Completion of testing

1/17/2023

1st scheduled launch to occur in production

Launch has been delayed per Felicia

1/20/2023

Final version of template has been provided by Exam Development

1/23/2023

Test emails have been generated and sent to Exam Development and Exam Admin team to verify contents.

1/24/2023

Emails sent to candidates

1,480 emails sent including those to 4 internal addresses for QA process

Not Doing


Supporting Documents

View file
nameFREE ASWB TEST SUPPORT.msg
View file
nameOne last tweak .msg
View file
nameTMI Brochure_v5.1[34367].pdf

...