Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.
Page Properties


Target release

Epic

Document

Project status

Status
colourGreen
title

DRAFT

COMpleted

Project Manager

Robert Adach

Business POC

Dave Ryckzo

Designer

Robert Adach

Developers

Robert Adach

QA

Robert Adach


Table of Contents

Table of Contents
maxLevel4
minLevel2


...

Background and Overview

...MA applicant's are submitting phone & email inquiries to the MA board instead of MSERV. We are working with the MA board to solve this problem. ASWB contact info is properly posted on ASWB's landing page, the online apps, etc., but applicants still contact MA, and then us, with inquiries that possibly could be resolved with informational direction.,, 

Scope

  • As stated in LMR-6012 

MSERV is working with MARCOM to develop an informational postcard that we intend to mail (and then email) to MA licensure applicants with brief application process instructions as well as our contact info. We would like to request IT create a monthly rolling spreadsheet (attached) (automated or manual) with each MA applicant's name/address/email information to be submitted to MARCOM's printer vendor for creation and mailing of a marketing postcard to all MA LAP applicants on a certain date every month...

Terminology

  • LapMgr - The LAP Manager application used by Member Services to process Massachusetts applications submitted online.

  • Business POC - The business lines point of contact who will be responsible for all communication with the Project owner for the business lines involvement in this project.


...

Requirements

Title

Description

Notes

1

Report Layout

The system will generate an excel file with the fields detailed in the "File Format and Details" section of this document

  • Must generate as a valid XSLX formatted file

2

Report Content

The system will include the distinct information details outlined in the "Report Definition" below for any application imported into the LapMgr system during the previous month regardless of the applications current status. Applications handled in the PreApp (paper apps/updates) will not be included.


3

Report Content

The system is not expected to exclude applications from the list by any means other than the Import Date


4

Report Content

Any field which does not contain a value in the LapMgr database will be listed as an empty field in the output file


5

Report Delivery

The system will deliver the generated file via email using an email as defined in the Email Definition section of this document.


6

Report Recipients

The system will be able to deliver the report to one or more recipients. Changes to the recipients must not require code changes

Initial recipient list is: Kim Philips, Keeley Cook, Jami Soedler, Dave Ryzcko

7

Report Generation

The system will generate the report on a monthly basis via a scheduled task.


8

Report Generation

The system is not expected to retain a copy of the generated report once it has been sent.


9

Error Handling

The system will be expected to provide a detailed log of any errors encountered during the creation of the report, email or its delivery

*Delivery issues up to and including the handoff to the ASWB mail system. This will not include reporting/logging of bounce back or other delivery failures that result from the recipients mailbox

10

Monitoring

The system will immediately notify IT staff (to the extent it is possible) of any failures or errors encountered with the the report creation and email process.


File Format and details
Anchor
FileFormatsAndDetails
FileFormatsAndDetails

Report definition
Anchor
ReportDefinition
ReportDefinition

File type: XLSX

Column Name

Data Format Type

Source

Notes

1

First Name

Text

LapMgr

2

Last Name

Text

LapMgr

3

Address 1

Text

LapMgr

4

Address 2

Text

LapMgr

5

City

Text

LapMgr

6

State 

Text

LapMgr

7

Zip

Text

LapMgr

8

Email

Text

LapMgr

Email Definition
Anchor
EmailDefinition
EmailDefinition

Field

Value

Notes

From

ASWBServices@aswb.org


To

Report users

Defined as a configuration setting so it may be updated via a database change w/o any coding changes or deployment needed

Subject

Massachusetts Application list for <<Reporting Period>>

The <<Reporting Period>> will be the full month and year value such as July 2021.

Body

The attached document includes all Massachusetts emails imported into LapMgr during <<Reporting Period>>

The <<Reporting Period>> will be the full month and year value such as July 2021.

Attachment(s)

XLSX file generated as part of process

File is defined in the File Format and details section of this document

User interaction and design

  • Not applicable as this will be run via an automated process managed by IT

Questions

Below is a list of questions to be addressed as a result of this requirements document:

Question

Outcome

Specific exclusions from score

  • The system will not support sending the report to non-ASWB members. Additional effort will be needed to ensure email is sent via encrypted mail to external sources.

  • The system will not support generating the report with a custom date range. Requests for reports with a timeline other than the previous month will be handled by IT via a Jira ticket.

  • Applications listed in PreApp are not included in the report.

  • The system will not keep a copy of the generated report once the email has been generated and handed to the mail provider.

  • The system will not exclude applicant information from the report except based on the import date of the associated applications.

  • The system will attempt to sanitize any data used in the report.

  • The system will not attempt to validate the address listed by the applicant against the USPS address verification services

  • The system will not attempt to validate the format of the email address of an applicant

  • The system will not be expected to remove or distinguish email addresses listed on any DNC list administered by ASWB.


Timeline

#

Title

Start Date

Promised Completion Date

Actual Completion Date

Status

Notes

1

Project Kick-off

 

N/A

N/A

Status
colourGreen
titleIn Progress

2

Requirements Gathering

 

 

 

Status
colour

Green

Purple
title

IN Progress

Complete

3

Dev Design

 

 

 

Status
colour

Green

Purple
title

In Progress

COMPLETE

4

Mock ups delivered

N/A

N/A

N/A

Status
colour

Green

Purple
title

In Progress

COMPLETE

5

Requirements Sign-off

Status
colourPurple
title

Not Started

COMPLETE

Received approval via ticket update in LMR-6012

6

Development

*

*

Status
colourGreen
title

Not Started

In progress

7

IT Testing

*

*

Status
titleNot Started

8

Stakeholder testing

*

Status
titleNot Started

9

Production release

Status
titleNot Started

10

Project post mortem

Status
titleNot Started

Potential impacts to timeline

  • A change in IT development project calendar due to new and higher priority development requests may force the delay in one or more deliverables.

  • The development and IT testing efforts may not require as much effort as anticipated, and may result in Stakeholder testing being available at an earlier date.

  • The development timeline (7/26/2021 - 7/29/2021), IT testing (7/30/2021) and Stakeholder testing (8/2/2021) timelines, are based on approval by Member Services Management to begin the project work being received by no later than 7/23/2021.

...

Technical Review (IT)

Areas Affected

  • DevOps Toolbox

Implementation

  • Add item to DevOps toolbox

  • Set monthly job to print report

Effort

  • Based on the requirements listed, IT expects that Development of the requested item and complete testing will consume approximately 4-8 hours of effort.

  • This request does not impact any other planned or projected work effort of the IT development team

...