Target release

Epic

Document status

DRAFT

Document owner

Robert Adach

Business POC

Designer

Developers

QA

Goals

  • Notify applicants of failing score reports

  • Notify applicants of passing score reports

  • Track each exam result for an applicant approval

Background and strategic fit

The ASWB Licensing Services team requires that the applicants of the pre-approval applications for CO, UT & TX that they process are properly notified of next steps when they have passed or failed their exam. The team also requires that the system track the number of tests and the results of each taken by an applicant for reporting purposes.

Assumptions

  • The requirements for this project apply to all pre-approval applications processed by ASWB Licensing Services team.

  • All communications with the applicant will utilize the same templates, with replaceable jurisdiction information (name, email, URL, etc.)

  • The system will only consider exam results for an applicant for the same exam level as indicated on their application, and within the approval period of the application.

Requirements

User Story

Importance

Notes

1

As a system, I must notify an applicant via email of a failing exam score

Must Have

2

As a system, I must notify an applicant via email of a passing exam score

Must Have

3

As a system, I must track the number of exams and results (Pass/Fail and Date) of each exam attempt for an applicant/application

Must Have

Raw/Scaled scores, test center, etc. are not required to be tracked at this time.

4

As a system, I must change the status of an application based on the exam result received

Must Have

5

As a system, I must notify ASWB IT of any issues with processing

Must Have

Questions

Below is a list of questions to be addressed as a result of this requirements document:

Question

Outcome

Who will be the main point of contact for the Licensing Services team for this project?