Summary for the week ending August 26, 2021
Current project health | Current project status | Project constraints |
---|---|---|
ON TRACK | Webpages: Initial development is complete and test case documentation and validation is beginning Legacy Applications: crcRegistration:
crcManagement:
Pearson Vue file creation:
| Awaiting final text for error messages associated with new fields and questions which have been altered. |
Project status
Accomplishments
Initial development of the new registration web pages has been completed and the team is able to successfully process registrations adhering to all documented data validation and business rules.
Changes to the crcRegistration and shared code within the legacy applications been completed for creating new and editing existing registrations and the team is able to successfully process registrations adhering to all documented data validation and business rules.
Next steps
IT plans to complete the first end-to-end registration (from entry through import) on or before 9/3/2021
IT team will document and validate the test cases needed to ensure full coverage of possible scenarios
CSC Team (Felicia) to provide the updated error messages to be used so final code changes can be made and appropriate test case documentation screenshots can be taken.
Risks & project issues
Continued changes to questions, answer options or logic may result in delays of testing and handoff to CSC
All further changes will be subject to the IT Development change management process and will require Senior Management approval.
Development team has reduced capacity for September due to staff vacations