2021-09-03 - EREG
Summary for the week ending September 3, 2021
Current project health | Current project status | Project constraints |
---|---|---|
ON TRACK | Webpages:
Legacy Applications: crcRegistration:
crcManagement:
Pearson Vue file creation:
| Awaiting final text for error messages associated with new fields and questions which have been altered. |
Project status
Accomplishments
Initial development of the new registration web pages has been completed and the team is able to successfully process registrations adhering to all documented data validation and business rules for new registrations.
Changes to the crcRegistration and shared code within the legacy applications been completed for creating new and editing existing registrations and the team is able to successfully process registrations adhering to all documented data validation and business rules.
Several end-to-end tests (Candidate Registration through Import) have been successfully completed.
Next steps
Complete testing of Custom Race question
Complete testing of error logging.
IT team will document and validate the test cases needed to ensure full coverage of possible scenarios
CSC Team (Felicia) to provide the updated error messages to be used so final code changes can be made and appropriate test case documentation screenshots can be taken.
Risks & project issues
Continued changes to questions, answer options or logic may result in delays of testing and handoff to CSC
All further changes will be subject to the IT Development change management process and will require Senior Management approval.
Development team has reduced capacity for September due to staff vacations
This reduction was accounted for in all development tasks and timelines.